Every one of 19 March 9 LEAP-listed Small District Modernization allocations matches a specific requested project; 104 remain unknown
Finding
The Small District Modernization request lists 123 projects: 23 construction projects totaling $127,310,000 and 100 planning projects totaling $3,354,000. The March 9, 2026 LEAP Capital Document lists 19 funded allocations: 12 construction totaling $70,832,000 and 7 planning totaling $274,000. Every one of the 19 listed allocations matches a specific requested project by project type, district name and legislative district at the same requested amount, and no listed allocation is unmatched. The remaining 104 requested projects are not on that list, and their status is unknown; this release does not describe them as not funded, denied or unsuccessful. Planning request row 82, previously recorded with an unidentified district, is Willapa Valley at $35,000, and is not on the list.
- Requested amount
- A dollar figure appearing in an OSPI decision-package fiscal table or fiscal-detail block, as published in OSPI's own 2026 supplemental budget request documents. Not an appropriation, disbursement or receipt, and the retained evidence does not record who received the request or when.
- Matched allocation
- A dollar figure on the March 9, 2026 LEAP Capital Document that identifies the same project type, district name, legislative district and dollar amount as a specific pre-enactment Small District Modernization request. Establishes which request a listed allocation names, not district receipt or spending.
What happened to the 104 unmatched small district modernization projects? Their status is unknown. They do not appear on the March 9, 2026 LEAP list, but that does not mean they were not funded, denied or unsuccessful.
Material qualifications
- The 104 small district modernization projects with no match on the March 9 LEAP list have an unknown status; unknown is not the same as not funded, denied or unsuccessful.
- A matched allocation on the March 9 LEAP Capital Document identifies which request a listed dollar figure names; it does not establish that a district received or spent that money.
Exact quantities
Scroll horizontally to see all columns.
| Quantity | Value | Unit | Denominator | Uncertainty |
|---|---|---|---|---|
| Total requested, 23 construction projects | $127,310,000 | USD | n/a | Point figure as printed or amended in the retained primary text; no distributional uncertainty quantified. |
| Total requested, 100 planning projects | $3,354,000 | USD | n/a | Point figure as printed or amended in the retained primary text; no distributional uncertainty quantified. |
| Total LEAP-listed allocation, 12 construction projects | $70,832,000 | USD | n/a | Point figure as printed or amended in the retained primary text; no distributional uncertainty quantified. |
| Total LEAP-listed allocation, 7 planning projects | $274,000 | USD | n/a | Point figure as printed or amended in the retained primary text; no distributional uncertainty quantified. |
| Requested amount, Willapa Valley planning grant (row 82, not on the March 9 list) | $35,000 | USD | n/a | Point figure as printed or amended in the retained primary text; no distributional uncertainty quantified. |
How the evidence supports this finding
A listed allocation that agrees with a requested project on type, district name, legislative district and dollar amount identifies which request it names; a control that breaks one of those fields fails the same join.
How many of the 123 SDM project requests match a later allocation list?
19 of 123 match the March 9 LEAP list; the other 104 have an unknown status, not a not-funded status.
The 104 small district modernization projects with no match on the March 9 LEAP list have an unknown status; unknown is not the same as not funded, denied or unsuccessful.
Sources and calculations:
Evidence that could change the finding
A later or more complete allocation list, or district-level spending records, could match more of the 104 currently unmatched projects.
Sources and calculations
Scroll horizontally to see all columns.
| Evidence | Locator | Source | Publisher |
|---|---|---|---|
| 23 requested construction projects | data selection: project_type, priority_rank, legislative_district, school_district and requested_amount fields; the 23 construction rows in sdm-project-ledger.csv; no construction rows excluded | Small District Modernization construction-project appendix | Washington Office of Superintendent of Public Instruction |
| 100 requested planning projects | data selection: project_type, priority_rank, legislative_district, school_district and requested_amount fields; the 100 planning rows in sdm-project-ledger.csv; no planning rows excluded | Small District Modernization planning-project appendix (Appendix B) | Washington Office of Superintendent of Public Instruction |
| 19 LEAP-listed allocations matched to 123 requested projects | data selection: project_type, legislative_district, school_district, requested_amount and status fields; the 19 rows in sdm-project-ledger.csv marked matched_to_listed_allocation, out of 123 total rows; 104 rows excluded as not on the March 9 list, status unknown | LEAP Capital Document No. OSPI-1-2026, Developed March 9, 2026 | Washington State Legislative Evaluation and Accountability Program (LEAP) Committee |
| Planning row 82 reads Willapa Valley | record: priority_rank 82 in the planning rows of sdm-project-ledger.csv | Small District Modernization planning-project appendix (Appendix B) | Washington Office of Superintendent of Public Instruction |
SDM requested and matched totals by project type
requested_total(type) = sum(requested_amount where project_type = type); matched_total(type) = sum(requested_amount where project_type = type and status = matched_to_listed_allocation)
Rounding: Whole-dollar arithmetic.
The 123 requested projects were joined against the 19 LEAP-listed allocations by type, district name, legislative district and amount, and a deliberately wrong project-type control fails the join while the unmodified join passes; see checks/sdm-join.json.
Data, code and downloads
Every file this finding rests on. Figures carry their own download links beside them.
- Small District Modernization project ledger, 123 rows
Every requested Small District Modernization project: type, priority rank, legislative district, school district, requested amount, whether it matches a March 9, 2026 LEAP-listed allocation, and the listed amount where there is one.
- Small District Modernization join receipt
The join of 123 requested projects against 19 LEAP-listed allocations, and its deliberately wrong control.
- SDM sums recipe
Recomputes the SDM requested and matched totals from the admitted 123-row ledger.
Later changes
Updates to this finding. Corrections and withdrawals are listed with the current answer.
Use this research
Penner Strategy. "Every one of 19 March 9 LEAP-listed Small District Modernization allocations matches a specific requested project; 104 remain unknown". What OSPI requested in its 2026 supplemental budget, and what the enacted budgets appropriated. Version 0001. September 12, 2026. https://pennerstrategy.com/research/ospi-supplemental-budget-requests/editions/0001/findings/f-sdm-project-matching/. Qualification: The 104 small district modernization projects with no match on the March 9 LEAP list have an unknown status; unknown is not the same as not funded, denied or unsuccessful.